Ground-up new development of a high-end 2,500 SF carriage house inclusive of a three-car garage with roof deck that ties into the existing two-family structure. (7-month timeframe)

  • Pre-construction and onsite management determined several faults within preexisting drawings that were remediated prior to installation saving client time and money
  • Coordinated very logistically challenged footing/foundation placement – this was completed in (15) separate placement sequences
  • Framing of entire structure including complicated dormer windows and roof structure
  • High-end slate roof installation
  • Installation of Pella windows
  • Installation of 20-foot garage door and 8-foot garage door
  • New underground plumbing and electrical tied into existing structure
  • New 3-zone central heat and air conditioning system installed minimizing soffits
  • New Hardie siding installed on new and existing structure as well as replacement of old windows
  • Installation of two custom bathrooms and kitchen